Client: USACE, Omaha District
Location: Fort Carson, Colorado
Contract Value: $3M
The 47th Brigade Combat Team (BCT) Power and Communications Infrastructure project involved the design-build design, construction and installation of a substation and communications node at Fort Carson, Colorado. The Tepa team moved all of the electrical lines from overhead to underground. The team used a custom-made switchgear and a 34.5 KV line tied to the main city grid to re-feed circuits #10, #13 and #14 on the installation and Evans Army Community Hospital.
The project also involved the following:
- Three miles of a circuit (Circuit 11) out of the new substation, including all communications lines, primary vaults, switchgears and transformers
- Evans Army Community Hospital re-fed out of a new substation through Circuit #14
- Street light poles
- All communications pathway conduit
- All concrete duct bank
- All conduit piping for the primary MC350 cable and cable installation